FIRST-ADASA GROUP LIMITED has fully mobilized personnel and equipment base for all
aspect of marine, dredging works and oilfield activities in Nigeria. We have a base office at
Nigeria Police Force Estate Chinue Worlu Drive, Off Sani Abach Road G. R. A. Phase 3, PortHarcourt, Rivers State, a Base Jetty in Port-Harcourt and Jetty in Yenagoa. Presently, both
jetties are less than 50% utilized.
1.1 Total Area
FIRST-ADASA GROUP LIMITED has a jetty facility located adjacent to the Naval Yard at
Rumuolumeni, Port-Harcourt. The jetty has an area in excess of 30,000m2
and possible
expansion of same on one side and across the water front. The Company also has a jetty
facility at Yenagoa, beside the Government Jetty, which has an area in excess of 35,000m2
.
1.2 Details of Assembly Area
One unique aspect about our jetties is that they were constructed in similar ways. The jetty
facilities consist of both open and covered fabrication area. The covered areas are used for
fabrication of onshore platforms and other minor to medium level pre-fabrication works.
1.3 The Jetty facilities have the capability to construct topside and jackets but not concurrently.
Our jetty adjacent to the Naval Shipyard can construct topside and jackets concurrently if
need be, by making use of the Naval Shipyard or Nigerian Ship Builders facility. We have an
agreement with both organizations.
1.4 We have an adequate storage e area for storage for materials. This includes a covered
warehouse and an open fenced area belonging to FIRST-ADASA GROUP LIMITED. This can
be prepared to accommodate the anticipated level of storage required for this type of Project. We are presently not making use of this, as we do not presently have any need for
it.
1.5 Opposite the two jetties are covered workshops with lathe machines and adjacent offices.
1.6 We do not have any restrictions to load out and sail away from our jetties. The open rivers are dredged to accommodate big barges.
1.7 Our present load-out capacities are in excess of 10,500 tons.
1.8 We also have sand dredging sites, where sales of sand are made.